connect your electricity today

Obtaining technical conditions for connecting electricity from 15 kW is real!

Having purchased a plot of land in the Tver region for development, you are faced with a problem - lack of electricity. Yes, earlier, when you were bargaining with its previous owner, the presence of light was unimportant, since the price suited you quite well, however, time sets priorities in its own way. Construction without electricity is difficult.

In which direction to move and where to start, read on.

Electricity registration

Connecting electricity to a private home begins first of all with drawing up the appropriate technical conditions. This documentation is managed by the local power grid organization, and in particular by its department such as the CSC (public service center).

Documents required to obtain technical documentation for a land plot in the Tver region as a whole:

  1. — passport and its copy with the registration page;
  2. - certificate of land;
  3. - certificate for the house or a copy thereof;
  4. — site plan (or a copy thereof);
  5. — an application to the CSC for connecting electricity to a country house (in two copies - for yourself and for the organization).

Electricity networks do not have the right to refuse to complete the relevant documentation. By law, the electric network must consider your application for no more than 30 days; after this period, an agreement must already be concluded between you and this organization with the issuance of technical specifications.

Connection procedure

Before submitting an application to connect a plot of land to electricity, you need to calculate the required power that all potential equipment on the territory will likely consume.

It is definitely worth taking into account the fact that in the future some equipment may be purchased additionally, so the power should be calculated with a margin.

Many people connect electricity to their garden plot only in the summer, without intending to use many electrical appliances.

However, if there are plans to apply to connect electricity to a plot of land for the construction of a permanent structure for the purpose of permanent residence, then the following possible additional electricity costs must be taken into account:

  • connection of energy-intensive equipment for opening gates, barriers, garage doors,
  • connection of automatic watering devices,
  • connection of alarm systems, special devices to ensure the safety of residential buildings and territories,
  • providing electricity to video surveillance devices in the occupied space,
  • connecting equipment for heating water in the house or on the site (for example, a washing tank),
  • provision of light lighting on the site,
  • providing electricity to additional buildings.

How to abandon a plot of land so as not to pay taxes?

If the documentation with the technical characteristics of the electrical circuit and the equipment transmitting electricity is ready, it is worth starting to create a technical plan for the placement of electrical equipment and networks.

To create a plan that takes into account all the features of the objects located on the land plot, you need to contact the design organization that is responsible for such activities.

After the project has been approved, you should contact the energy supply organization to connect the site to the network, install the meter and seal it after performing the required technical actions.

After all the above work and approvals have been completed, you need to make sure that you have the following documents:

  • confirming compliance with the required conditions for connecting electricity to the site,
  • fixing the boundaries of the area that is to be connected to the electrical network,
  • information about the maximum power of equipment, operational documentation,
  • confirming the connection of the land plot to the electricity network using transmission equipment.

Sample power of attorney for the sale of a house with land

Whether a land plot that is owned can be seized, read here.

Is it possible to disconnect debtors from electricity in SNT? Read the link: https://novocom.org/snt/mozhno-li-v-snt-otklyuchat-dolzhnikov-ot-elektrichestva.html

Note! It may take several months to agree on all the details. It is worth determining in advance the type of cable and the method of connecting the land plot to the electricity network.

There are two methods of connecting to the network: overhead and underground.

Mechanism for connecting a plot of land to the electrical network:

  • calling an employee to connect electrical equipment to the network,
  • creation of documentation with the specified technical indicators and conditions for connecting the land plot to the electrical network,
  • coordination of compliance with technical requirements,
  • direct production of work,
  • obtaining documentary evidence of the connection of the site to the electrical network,
  • signing documentation stating that the applicant has listened to information about safety precautions and the correct use of electrical networks,
  • connect the meter and pay for the sealing of devices receiving electricity,
  • draw up an agreement with the electricity supply organization for the provision of electricity within the specified tariff.

It is worth knowing that it is not difficult to record the location of objects; this can be done independently and without the help of outside forces.

The main task of the selected design organization is not only to create a power supply scheme for the site and facilities on it, but also to coordinate the design documentation with utility services and other companies in a short time frame, since it will be difficult for the site owner to independently obtain the required permits and documentation.

Watch the video. Connecting electricity to the site or to a private house:

Direct connection to electrical networks

When you receive the documentation, please read it carefully. The power grid organization may include so-called excess requirements in the contract.

The most common violations of the rights of individuals occur on such items as connecting electricity up to 15 kW to the house. Individuals are required to complete a power supply project. This is an excessive requirement, according to the Town Planning Code of the Russian Federation (clause 3 of Article 48).

After signing the contract, you should begin to fulfill the technical conditions specified in the documentation.

As a rule, this is the following set of standard actions:

  1. — installation of a metering unit (outer wall of the house/ overhead line support);
  2. — installation of wires from the metering station to the border of the land plot;
  3. — installation of networks inside the house (if it is fully built).

Project preparation

During the development of a project or drawing, you will need to depict an external power supply diagram. When creating project documentation, you need to take into account many nuances, so the right decision would be to seek the help of a professional.

Most often, the project is a unique object, that is, there are practically no two identical options. Therefore, in such a matter, assistance will certainly be required in its development. Here it is necessary to take into account both the features of the technical plan and the desires of the owner of the future building.

Read more: Mandatory and dispositive norms in the Constitution of the Russian Federation

It is worth carefully considering the location of the transformer, as well as the conductivity of the supplied cables. If a single-line diagram is used, then it is necessary to take into account where the sources of electricity will be located.

The right decision would be to discuss the details of interest before an agreement on the supply of electricity is concluded. In another situation, it may happen that there is no chance to install lighting on the territory.

Installation of power supply also involves taking into account elements of heating equipment. The right solution would be to use those elements that reduce electricity consumption costs.

In particular, these can be heated floors and thermal pumps. In addition, some clients value such a category as security.

It is necessary to consider whether video cameras and alarms will be installed on the territory. These nuances should be thought through in advance to avoid negative consequences.

Sample application for connection to electricity

The universal form used to draw up the application is presented in Appendix No. 6 of the Decree of the Government of the Russian Federation No. 588. The document contains the following information:

  • personal information about the applicant (full name, passport details, registration address and place of residence);
  • reason for electrification of the site (construction, reconstruction, expansion, increase in operating capacity);
  • maximum power values ​​of electrical appliances, indicated in kW;
  • power supply reliability category;
  • terms of construction and commissioning of the facility;
  • list of documents attached to the application;
  • applicant's signature;
  • Date of preparation.

A sample application for electricity connection is available here.

To submit an application, a citizen must contact the energy sales company or send documents by mail.

The application is reviewed within 30 calendar days. After this period, the citizen is sent a list of technical conditions, the fulfillment of which is required for the electrification of the site.

Electrical connection

At the stage of building a house or when putting it into operation, the main task of the owner is connecting to electrical networks . To perform this task, qualified assistance is required at all stages, from calculating the technical characteristics of the power supply input and drawing up technical specifications to electrical installation work. You can save time, effort and budget by contacting ProfEnergoMontazh.

We will quickly connect electricity to a site , a private house, or outbuildings using the power grids of IDGC-Center PJSC. According to the law, the service organization must be the one whose electrical networks are located at the closest distance from the boundaries of the site. Thus, connecting electricity in Lipetsk , village. Dachny, Matyrsky in the village. The connections are made to the power grid facilities of JSC LGEK. The rest of the Lipetsk region is served by IDGC-.

Stages of technological connection to networks:

1. Obtaining technical specifications (technical conditions). To do this, you need to submit an application to the energy company, which is accompanied by a list of groups of electricity consumers. The package of documents also includes a document on ownership (for a house, for a plot), a passport, a topographic survey or a situational plan. ProfEnergoMontazh specialists submit applications only on the basis of a notarized power of attorney.

Application acceptance addresses:

    • JSC "LGEK" - Lipetsk, st. Tolstogo, 23a, office. 103 (1 floor);
  • PJSC IDGC - Lipetsk, Oktyabrskaya St., 22 (for all districts of the Lipetsk region), or to the representative office of Regional Electric Networks. It is also possible to submit an application through the electrical network services portal

2. Design. Specialists carry out an external electrification project reflecting information about the location of cables and communications, the brand of the input circuit breaker, grounding, the location of current receivers and their power, and the distribution cabinet. Before starting the physical connection of electricity to the house , the design documentation is approved.

3. Electrical installation work. When connecting electricity to a plot of land or a private property, cables from the external network are laid, a meter and other equipment are installed according to the project, and wiring is carried out throughout the plot and house.

4. Checking compliance with specifications. After electrical installation work, the authorized body checks the compliance with the specifications and the correctness of the electrical installation. Based on the inspection conclusions, ETL (Electrical Technical Laboratory) Test Certificates and Certificates from the power supply company are issued, after which the electricity connection to a private home can be considered complete.

List of required documents

You need to send an application for connection to the organization that services the nearest transformer point or power transmission line (PTL). The citizen is provided with the following package of documents:

  • statement;
  • passport;
  • title document for the land plot and the private house located on it;
  • copy of TIN;
  • list of devices consuming electrical energy (indicating power);
  • boundary plan of the site indicating the proposed location of power line poles.

IMPORTANT! If utilities (gas pipeline, water supply, sewerage) pass through the site, they are also displayed on the boundary plan.